King of Prussia – A series of travel restrictions and the reopening of an off-ramp are scheduled this week (Aug. 16-22) on Route 202 between Paoli Pike and High Street in West Goshen Township, Chester County, as crews continue to replace deteriorated concrete pavement on the four-lane highway, the Pennsylvania Department of Transportation said today.

Weather permitting, the contractor’s schedule for this week is:

• From 10 p.m. Monday (Aug. 16) to 5 a.m. Tuesday (Aug. 17), northbound Route 202 will be reduced from two lanes to one between the Westtown Road and Paoli Pike interchanges for shoulder construction;

• From 10 p.m. Tuesday (Aug. 17) to 5 a.m. Wednesday (Aug. 18), southbound Route 202 will be reduced from two lanes to one between the Paoli Pike and Westtown interchanges to restripe travel lanes for barrier placement along shoulder;

• From 10 p.m. Wednesday (Aug. 18) to 5 a.m. Thursday (Aug. 19), southbound Route 202 will be reduced to one lane between Matlack Street and High Street for barrier relocation and traffic line painting for a traffic pattern change;

• From 10 p.m. Wednesday (Aug. 18) to 5 a.m. Thursday (Aug. 19), northbound and southbound Route 202 will be reduced from two lanes to one between the Paoli Pike and Westtown interchanges for shoulder construction;

• From 10 p.m. Thursday (Aug. 19) to 5 a.m. Friday (Aug. 20), northbound and southbound Route 202 will be reduced from two lanes to one between the Westtown Road and Paoli Pike interchanges for shoulder construction;

• From 10 p.m. Thursday (Aug. 19) to 5 a.m. Friday (Aug. 20), northbound and southbound Route 202 will be restricted to one lane between Matlack Street and High Street for barrier relocation and pavement saw cutting;

• From 10 p.m. Thursday (Aug. 19) to 5 a.m. Friday (Aug. 20), crews will reopen the southbound Route 202 off-ramp to High Street; and

• From 10 p.m. Friday (Aug. 20) to 5 a.m. Sunday (Aug. 22), northbound and southbound Route 202 will be restricted to one lane between Matlack Street and High Street for the replacement of deteriorated concrete pavement.

PennDOT advises motorists to allow more time for travel along Route 202 during construction because backups will occur. This work schedule is dependent on the weather.

The road construction on Route 202 is part of PennDOT’s $19,377,081 project to rehabilitate and improve 4.3 miles of Route 202 between the Route 100 Interchange and High Street in Chester County. The project is funded through the American Recovery and Reinvestment Act.

Allan A. Myers, LP of Worcester, Montgomery County is the general contractor on the federally-funded project, which is scheduled to finish in Dec. 2011.

PennDOT reminds motorists they can log on to 511pa.com or call 511 from any phone to check traffic conditions on major highways before heading out.